Our remit was to excavate and deal with muck arising from the construction of a storm defence shaft which is 80metres in diameter and 30 metres in depth. Fox initially stripped the topsoil in to mounds. We then remodelled the site and surrounding area with the large amount of material arising from the shaft excavation before re soiling the whole area. In addition we excavated to form swales to act as further attenuation as well as stoning up 1500m of footpath.
Finally we placed our recycled no-fines material as sub formation to the new MUGA pitch being constructed.